Bruny Main Road Upgrades
|
BackgroundThe Department's long term objective is to provide a continuous sealed road between Bruny Island's major population centre of Alonnah and the ferry terminal at Roberts Point.The following projects have been identified as priority road upgrades along Bruny Main Road; | ![]() |
- Sealing of a 3.6km section at Great Bay - between Whaymans Road and Great Bay
- Adventure Bay junction to Alonnah - reconstruction of approx 2kms of road
- The Neck and Great Bay Road - road embankment stabilisation
- Sealing of 800m of gravel road travelling South from William Carte Drive
- Murphy's Creek Bridge replacement at Alonnah
1. Great Bay - Road ReconstructionThe first of these upgrades, sealing from Whaymans Road to Great Bay, was completed in November 2010. This $3.4M project will improve safety for both residents and tourists and reduce maintenance costs. Works included widening the road pavement, improving drainage and sealing of the existing gravel road surface. | ![]() |
2. Adventure Bay Road Junction to Alonnah - Road Pavement Renewal
In November 2010, work commenced to upgrade sections of existing road pavement on Bruny Main Road from Adventure Bay Road Junction to Alonnah. This work was completed in December 2010.
This $300,000 project included improving the road surface and upgrading approx 2.5kms of road pavement, including improved road drainage.
3. Road Embankment Repairs to the Great Bay and the NeckErosion of the road embankment caused by storm damage and wave action has been repaired and the embankment strengthened at Great Bay and at the Neck. Works were completed from August to November 2010. The $250,000 project included repairs to the road shoulder and reinstatement of the road embankment. 4. Road Sealing at Alonnah DIER intends to seal approx 700m of gravel along Bruny Main Road at Alonnah, travelling South from Willian Carte Drive to 50km/h end speed sign. These road sealing works are programmed for February/March 2012.
5. Replacement of Murphys Creek BridgeDIER is committed to replacing the current bridge at Murphys Creek, Alonnah with a two-lane bridge and separated pedestrian footpath.Plans to build the replacement bridge during the 2011/2012 summer season have been deferred due to unexpected, recent identification of Aboriginal heritage at this site. Initial archaeological advice received in August 2010 cleared the project site of any Aboriginal issues. However a follow-up investigation conducted on 2 September 2011 identified a number of Aboriginal relics near Murphys Creek Bridge. DIER will investigate the heritage management options to enable the construction of the bridge whilst minimising the impacts on Aboriginal heritage values. The bridge will be replaced when all of the project constraints at this location are resolved.
Contact DetailsFor further information about the Bruny Main Road projects please call Steven Kaczmarski on (03) 6233 8084 or email steven.kaczmarski@dier.tas.gov.au | ![]() |