Budget Summary
Expenditure on Project as at 26 August 2011
- Expenditure on the Light Rail Business Case as at 26 August 2011 was $330,000, representing 94% of total budget expenditure. The expenditure is related to costs associated with project management, payment for consultancy services,tender initiation costs and support of the Community Advisory Panel.
- Two of the four reported items fell below budget, Tender advertising and meeting costs was under budget by $1,749, with Additional analysis and contingency under budget by $15, 316.
- The amount of the awarded contract for associated consultancy services was $226,688 (exclusive of GST) and this was fully spent.
- The amount spent so far for all items is displayed below.