The first four priorities include upgrades from North of Rosevears Drive to Gravelly Beach Road, Atkinsons Road to Waldhorn Drive, Exeter to Batman Highway and at Motor Road Junction.

About the project

The Department of State Growth is upgrading four sections of the West Tamar Highway. This project will improve the liveability of communities along the highway by making the highway safer, and improving travel time reliability to and from Launceston.

The contract to design and construct these four priority project has been awarded to Hazell Bros Pty Ltd.

1North of Rosevears Drive to Gravelly Beach Road

North of Rosevears Drive to Gravelly Beach Road

  • Road widening.
  • Sealed shoulders.
  • A new footpath on the eastern side.
  • Vegetation clearing and sight benching for better visibility.
  • Improved stormwater drainage.

Click here to enlarge the map.

North of Rosevears Drive to Gravelly Beach Road

2Atkinsons Road to Waldhorn Drive

Proposed upgrade:

  • shoulder widening
  • road resurfacing and line marking.

Click here to enlarge the map.

Atkinsons Road To Waldorn Drive

3Exeter to Batman Highway

Proposed upgrade:

  • new overtaking opportunities.

Click here to enlarge the map.

Exeter to Batman Highway

4Motor Road Junction

Proposed upgrade:

  • vegetation clearing and sight benching for better visibility.

Click here to enlarge the map.

Motor Road Junction location map

5Current situation

We’re currently working on preliminary designs for all four projects.

Work on the first project is expected to start in spring 2020, wioth all four projects expected to be complete in mid-2021.

6Community consultation

We created concepts for the proposed upgrades and asked people to let us know what they thought in May 2019.

The consultation period closed on Friday, 31 May 2019. You can see the comments left during the consultation period on our interactive map.

7Dates

Public consultation period: 18 – 31 May 2019

Construction: From Spring 2020

Contact

For more information about this project, please email participate@ghd.com.