We are rebuilding the road surface on the Lyell Highway, South of Tarraleah.

1About the project

The project is located on the Lyell Highway in the Central Highlands of Tasmania. The Lyell Highway runs from Hobart to Queenstown and is the main transport route to the West Coast of Tasmania.

2Timing

We will start work on Monday 8 November 2021 and should be finished in late March 2022, weather permitting.

We will be working on weekdays, between 7:00 am and 6:00 pm. We will let you know if we have to work outside these times.

3Traffic impacts

There will be a reduced speed limit and single lane closures during our working hours.

There will be some delays of up to 15 minutes during our work.

Road users should plan ahead and allow for up to 15 minutes extra travel time during this work.

Please follow the directions of traffic controllers and signs.

Contact

For more information about the project, please contact our Stakeholder Engagement Consultant, Louella Horne, on 0491 696 701 or by email, engagement@pittsh.com.au