Tasman Bridge Upgrade - Safety Barrier and Pathways
We are making the Tasman Bridge pathways safer for people who walk, wheel, and ride.
We are making the Tasman Bridge pathways safer for people who walk, wheel, and ride.
We have completed extensive technical assessments and have engaged with key stakeholders to develop a preferred design for the pathway upgrades.
The selected design is the best solution given the physical constraints of the bridge, the requirements of the project and it the available budget. It will improve safety and deliver meaningful improvements for active transport users.
We will be:
Once construction is complete and both pathways are operational, we will seek feedback on whether the pathways should be made one-way to improve flow and safety.
We have shared the designs from Tuesday, 28 October to Monday, 17 November 2025, to keep the community informed about what’s coming. Due to the safety requirements of the project and the constraints of the bridge, it is not practicable to make significant changes to the design.
See the Tasman Bridge Passing Bay design here
See the Tasman Bridge passing bay designs here (bird's eye view)
See the Tasman Bridge Safety Barrier design here
The Tasman Bridge is an iconic structure, and we actively manage it every day to keep it safe for users, including through regular maintenance inspections.
We are upgrading the Tasman Bridge pathways to make them safer for all users. In addition to improvements to the pathways, we will be improving connections to the bridge pathways first.
We are continuing work on the strengthening of the bridge’s deck to maintain the lifespan of the bridge and to allow for the current high volume of traffic to continue for many years to come.
We will also be upgrading the bridge’s lane use management system to help us better control traffic during peak periods and incidents.
We will also look at what needs to be done to manage the bridge for the rest of its life and what the future of the crossing should be.
This project will be built in stages. The eastern shore pathway connections to the bridge will be improved first, to lessen the impact on pathway users when we later close one pathway at a time to install the higher safety barriers.
Construction on the eastern shore pathways connections will start in late 2025.
The construction tender for the barrier and pathway upgrades will be advertised in late 2025, and work is expected to start in mid-2026.
We will aim to keep one pathway open to the public and will keep the traffic lanes of the bridge open to traffic during the day during construction.
We will work with the City of Hobart and other key stakeholders to see what improvements can be made on the western shore, including improvements to directional signage.
We will be raising the height of the barriers on a section of the western shore connection to the southern Tasman Bridge pathway where it separates from the offramp that connects to the Domain Highway. In this section, we will be retaining the existing barrier and installing new higher barriers at a height of 2.7 metres which will enclose the pathway, as shown in the preliminary design images below.
View preliminary design image 1 here
View preliminary design image 2 here
There will be no changes to the barriers or structure of the spiral pathway that connects the Tasman Bridge to the Intercity Cycleway on the western shore.
As part of upgrading the Tasman Bridge pathways, we will be removing the existing waterside barriers and replacing them with 3-metre-high barriers made out of stainless-steel mesh and powder-coated steel frames (as shown in the preliminary design image below. The mesh will be reinforced with wire rope cables, and a handrail will run along the length of the barrier at 1.2 metres above the pathway floor. This design will also be used in areas with passing bays.
View preliminary design image 3 here
Due to the safety requirements of the project and the physical constraints of the bridge, it is not possible to include physical aesthetic features in the barriers design.
We will be increasing the height of the roadside barriers to 1.2 metres. Existing barriers will either be retained and extended with new posts and a handrail or will be fully replaced with new 1.2 metre high barriers.
We will be installing an additional three passing bays on each bridge pathway, bringing the total to five per side, making passing safer and easier.
Each passing bay will be approximately 6 metres long, matching the existing design and will be spaced every 200 to 300 metres at select bridge piers (as shown in the preliminary design drawing below).
View preliminary design image 4 here
Due to the physical constraints of the bridge, longer bays are not feasible, as making them longer would move them further away from the support of the pier.
The crescent-shaped waterside barrier improves the sight distance for pathway users, ensuring the design meets the Australian Standard for sight distance (19 metres at 15 km/h).
Yes, the Tasman Bridge is safe to use. The Tasman Bridge was built to a design life of 100 years. We complete regular and extensive inspections and maintenance on the bridge as part of our ongoing management of this critical asset. The Tasman Bridge is inspected at least twice a week, and any maintenance issues are logged and scheduled for repair. Regular inspections and reports are part of our extensive program of planning, monitoring and maintenance to ensure this critical link in Hobart’s transport network remains in good shape for decades to come.
This upgrade will make the Tasman Bridge safer for pathway users through a range of improvements including:
We will also be completing bridge strengthening of the bridge’s deck to maintain the lifespan of the bridge. The bridge’s lane use management system will also be upgraded to help us better control traffic during peak periods and incidents. We will also look at what needs to be done to manage the bridge for the rest of its life and what the future of the crossing should be.
We developed and assessed several design options for the pathway upgrades. Each option was evaluated against our criteria of safety, accessibility, constructability, and how well it could be delivered given the physical constraints of the bridge and the available project budget.
The preferred design was selected because it offers the most practical and achievable solution and meets the project objectives of raising barrier heights, improving pathway connections, and maximising the available width for pathway users, including installing passing bays.
We did extensive technical assessments and engaged with key stakeholders and the design represents the most feasible solution.
This design also allows for continued access to electrical infrastructure and bridge maintenance during and after construction.
We are sharing the designs to keep the community informed about what’s coming. We welcome questions from the community about how the upgrades will be delivered and what they mean for pathway users.
However, due to the requirements of the project and the constraints of the bridge, it is not practicable to make significant changes to the design.
The original proposal, which we released to the community 2022, was to build wider pathways on both sides of the bridge to support more walking, wheeling and riding.
After the release of the original concept design, we completed further extensive engineering analysis and wind modelling to check the effects of the new, wider pathway design on the bridge. We found that while more than capable of supporting the current bridge and traffic volumes, some pile groups (the bridge’s underwater foundations) wouldn’t be able to support the significant extra loads of the wider pathways.
To build wider pathways we would need to make changes to the structure of the bridge, including major reinforcing and strengthening of the bridge’s piles. This significant work is not practical.
Because of these limits we are only able to progress the project with a design that does not increase loading on the bridge. Our planned upgrades will deliver still improve safety and deliver meaningful improvements for active transport users.
The preferred design includes additional width at handlebar and waist height and improved sightlines through crescent-shaped waterside barriers, as well as three additional passing bays on each pathway.
Detailed investigations showed that the original designs for wider pathways shared with the community in 2022 would increase the loading on the bridge.
Loading refers to the forces and loads that a bridge structure is designed to withstand. There are different types of loading:
Other things like earthquakes, temperature changes, and ground settlement can also affect loading on the bridge.
The Tasman Bridge has tall, narrow piles, and for sideways loading caused by wind the strength of the piles is critical.
Adding wider pathways on both sides of the bridge with taller safety screens would increase the self weight and wind load on the bridge, which means the loads on the piles would also be increased.
We are unable to install wider pathways on the bridge as we would need to make changes to the structure of the bridge, including major reinforcing and strengthening of the bridge’s foundations.
The strengthening we will be doing is on the bridge deck, to maintain its lifespan.
This is separate to the significant structure modifications, including major foundation reinforcing and strengthening that would be required to build wider pathways, which is not funded under the current project budget.
We are continuing to look at what needs to be done to manage the bridge for the rest of its life. We are also looking at the future of crossing, given that adding another lane to the bridge is not a viable option to cater for any future traffic increase.
We are doing some planning work to make recommendations on what needs to be done to manage the bridge for the rest of its life and identify appropriate ways to meet Hobart’s long term transport needs.
A lane use management system automates the switchover of the central lane of the bridge. This will improve flexibility in managing traffic during incidents and congestion. It will also improve safety for road users and bridge workers, by removing the need for field crew to be physically on the road to move bollards to switch the central lane.
The first phase of community consultation on the Tasman Bridge Pathways Upgrade project was completed on Tuesday, 19 July 2022.
We published the findings in the Tasman Bridge Pathways Upgrade Consultation and Feedback Summary Report (PDF 404.6 KB).
We will be constructing the project in stages. To allow the installation of higher safety barriers on the bridge pathways, the pathways connections on the eastern and western shores will be improved first.
The construction tender will be advertised in late 2025, and the pathway upgrades are expected to start in mid-2026.
We will aim to keep one pathway open to the public and will keep the traffic lanes of the bridge open to traffic during the day during construction.
Essential services and infrastructure, including a TasWater water main, run beneath the existing pathway flooring and require ongoing access.
A non-slip coating is regularly applied to the surface of the Tasman Bridge pathways to support safe access for people who walk, wheel and ride across the bridge. The quality of this surface will be inspected as part of upcoming inspections before the pathway construction starts.
We are aware of a groove along pathway edge that can affect bicycle tyres. We are unable to cover up this groove as we need to maintain access to the flooring, which are in base plate sections. The raised roadside barrier included in the design will shift people wheeling or riding across the bridge further away from the groove, reducing the risk.
We will keep the traffic lanes of the bridge open to traffic during the day during construction. We expect that there will be lane closures on the bridge overnight outside of peak times while this work is completed.
We will be working on one pathway at a time. We will aim to keep one bridge pathway open to the public during construction. We will communicate these closures and changes to pathway users ahead of and during construction.
The construction tender will be advertised in late 2025, and the pathway upgrades are expected to start in mid-2026. Work to upgrade the pathways is expected to take approximately 12 months to complete.
We are building the Tasman Bridge Pathways Upgrade project in stages. The first stage is constructing a shared path underneath the Tasman Bridge on the eastern shore. This will improve connections to the bridge pathways from Conara Road and Topham Street. These upgrades will help us to lessen the impact on people who use the Tasman Bridge pathways when we later close one pathway at a time to install the higher safety barriers.
In May 2025, we released a concept design to improve eastern shore pathway connections and sought feedback from the community and key stakeholders including the City of Clarence. We have now finalised the design, based on feedback received, including widening sections of the pathway to 2.5 metres.
We will be installing a 2.5-metre-wide shared path underneath the Tasman Bridge that connects the southern bridge pathway to Conara Road and Topham Street.
We will be doing landscaping and placing bollards to ensure safety for pathway users. There will be a handrail on the uphill sections of the shared path.
These upgrades will make it easier for people to walk, wheel or ride to access the Tasman Bridge pathways.
Construction is expected to start late 2025. View the design here.
We will work with the City of Hobart and other key stakeholders to see what improvements can be made on the western shore, including improvements to directional signage.
We will be raising the height of the barriers on a section of the western shore connection to the southern Tasman Bridge pathway where it separates from the offramp that connects to the Domain Highway. In this section, we will be retaining the existing barrier and installing new higher barriers at a height of 2.7 metres which will enclose the pathway, as shown in the preliminary design images below.
View preliminary design image 1 here
View preliminary design image 2 here
There will be no changes to the barriers or structure of the spiral pathway that connects the Tasman Bridge to the Intercity Cycleway on the western shore.
$130 million in funding has been committed by the Australian and Tasmanian governments for the Tasman Bridge Upgrade project, which includes the safety barrier and pathway upgrades.
In an emergency, call Triple Zero (000).
If you would like to find out more information and you have accessibility requirements, please contact the project team on the email below.
You can find out more about Transport Services' commitment to accessibility on our website here: https://www.transport.tas.gov.au/accessibility
If you have any questions, please contact the project team at tasmanbridgepathways@stategrowth.tas.gov.au.